Timelines

The following is a sample timeline for a full system implementation. The timeline at specific sites will vary depending on the complexity and readiness of the company.

Sample Timeline

Task No Task Description Days Relative to Go-live Days Duration Responsibility Resources Trip No
1 RF Site Survey -90 2 Sentai 1
2 Operations Review -90 2 Sentai 1
3 Interfacing to Hosts system Development -90 1 Sentai  
4 Interface from Host System -90 5 Host Provider  
5 Select Server -90 5 Client  
6 Internet Connection Ordered -90 1 Client  
7 Order RF Equipment -88 1 Sentai  
8 Warehouse Preparation -60 10 Client  
9 Order / Print License Plates -60 0.5 Client  
10 Configure RF Network -50 2 Sentai  
11 Install RF Network -40 2 Sentai  
12 Server Installation -40 1 Sentai  
13 Internet Connection Testing -39 0.5 Sentai  
14 Warehouse DB Loading -35 2 Sentai  
15 Install WMS Software -33 1 Sentai  
16 Interface Testing -32 2 Sentai 2
17 Pre Go-live Visit and Testing -30 3 Sentai 2
18 Overview Training -6 0.5 All 3
19 Manager Training -5 0.5 All 3
20 Operator Training -5 0.5 All 3
21 Go-live 0 0 All 3
22 Controlled Receiving 1 0.5 All 3
23 Observation & Training 2 7 Sentai 3
24 Post Go-live Review 60 2 Sentai 4