The following is a sample timeline for a full system implementation. The timeline at specific sites will vary depending on the complexity and readiness of the company.
| Task No | Task Description | Days Relative to Go-live | Days Duration | Responsibility Resources | Trip No |
| 1 | RF Site Survey | -90 | 2 | Sentai | 1 |
| 2 | Operations Review | -90 | 2 | Sentai | 1 |
| 3 | Interfacing to Hosts system Development | -90 | 1 | Sentai | |
| 4 | Interface from Host System | -90 | 5 | Host Provider | |
| 5 | Select Server | -90 | 5 | Client | |
| 6 | Internet Connection Ordered | -90 | 1 | Client | |
| 7 | Order RF Equipment | -88 | 1 | Sentai | |
| 8 | Warehouse Preparation | -60 | 10 | Client | |
| 9 | Order / Print License Plates | -60 | 0.5 | Client | |
| 10 | Configure RF Network | -50 | 2 | Sentai | |
| 11 | Install RF Network | -40 | 2 | Sentai | |
| 12 | Server Installation | -40 | 1 | Sentai | |
| 13 | Internet Connection Testing | -39 | 0.5 | Sentai | |
| 14 | Warehouse DB Loading | -35 | 2 | Sentai | |
| 15 | Install WMS Software | -33 | 1 | Sentai | |
| 16 | Interface Testing | -32 | 2 | Sentai | 2 |
| 17 | Pre Go-live Visit and Testing | -30 | 3 | Sentai | 2 |
| 18 | Overview Training | -6 | 0.5 | All | 3 |
| 19 | Manager Training | -5 | 0.5 | All | 3 |
| 20 | Operator Training | -5 | 0.5 | All | 3 |
| 21 | Go-live | 0 | 0 | All | 3 |
| 22 | Controlled Receiving | 1 | 0.5 | All | 3 |
| 23 | Observation & Training | 2 | 7 | Sentai | 3 |
| 24 | Post Go-live Review | 60 | 2 | Sentai | 4 |